Method

Tasks will be displayed bold when the status of the task has the 'TaskToDoTag'. The Administrator can set this up using the following method:

  1. Go to 'Maintenance' - 'Tables' - Table 'Status task';

  2. Open a status;

  3. Check the 'TaskToDoTag' and remove eventual other checkmarks at taskstatusclass;

  4. Click [Save] to save the changes.